Client : | Tilbury Douglas | Value : | £12.2m | Location : | Rotherham South Yorkshire | Time : | 4 Years |
- Precast twin wall 12m high wood store bunker walls
- Wood store pit and headwall – 6m high single sided RC walls, suspended headwall, jump form in-situ walls 12m high
- Bridge abutments and concrete deck
- Turbine bed – 2.4m thick concrete base on 6m high RC plinths and vibration pads
- Flood walls surrounding all key buildings including new substation and transformer blast walls
- Dry-shake power float floor slabs, grouted tarmac & concrete brushed finished yard areas
- All associated drainage, roads, yard slabs, grouted asphalt & hard landscaping
- Substation