Installation of new raft foundations and retaining walls to a Grade 3 waterproof standard. Confined space working within one of Leeds most iconic listed buildings.
Client : | Sir Robert McAlpines | Value : | £2.9m | Location : | Leeds | Time : | 3 Years |
- Installation of new raft foundations and retaining walls to a grade 3 waterproof standard. Confined space working within one of Leeds most iconic listed buildings
- 1400m2 waterproof raft slabs
- 155m shotcrete retaining walls
- 7 story slip form core
- New internal drainage
- Concrete to upper floors
- All form work Provided by Leeds Acro
- Restricted access working with confines of an existing building. Plant lowered into basement by hoist
- 2000m3 material excavated from basement and removed using conveyor systems
- Raft foundation works including core base construction
- Slipform Core