Education

Heslington Campus, University of York

Service Diversions, earthworks, ground stabilisation, foundations, concrete slabs, external works for 20 new student accommodation blocks, external works.

Client : Grahams
Value : £12m
Location : York
Time : 2.5 Years

  • Construction of Pile Caps, Ground Beams, Two Concrete Slip Form cores 19 and 15 Stories,
  • Underground Basement slab / Carpark, Access Ramp, Waterproofing and GAS Membrane works,
  • Ground floor slab and Podium + 18 Floors of Post Tension slabs,
  • Drainage and Ducting.
  • Building Height: 60m
  • Average Floor m/2: 1350m2 Using Topmax and Skydeck Panel.
  • Average Floor time Construction: 16 working days
  • Structural Concrete: 6750m3
  • Columns/Shear Walls Poured: 720 + 28
  • All form work Provided by Leeds Acro and Plant / Cranage by Moortown Plant